Chart 3: Residential delays easing, others have more work to do
Median number of days from consent issuance to final inspection by building type
Average
Maximum
Current
0
50
100
150
200
250
300
350
400
450
500
550
600
Houses
309
470
379
Attached dwellings
376
521
454
Residential alterations
374
553
521
Non-residential
259
489
440
Non-building
373
574
574