1 | The Games cost Victoria over $589 million |
---|
2 | The Department of Jobs, Skills, Industry and Regions' (DJSIR) business case for the Games was inadequate to support an informed decision by the government on the likely costs and benefits of hosting |
---|
3 | Agencies did not always work together effectively to give frank, full and timely advice to the government |
---|
4 | The original Games budget was unrealistically low, but the $6.9 billion cost estimate the government publicly released when it withdrew from the Games was overstated |
---|