The marina is a $33,6 million investment
Phase | Work | Start Date | End Date |
---|---|---|---|
Phase I | Construction of breakwaters to shield the marina, 140 docking points and a building with commercial space and apartments. | November 2019 | March 2021 |
Phase II | Construction of a second building with commercial space and apartments, and 35 additional docking points. | January 2020 | March 2021 |
Phase III | Development of a hotel and a convention center. | June 2022 | January 2025 |